Most kitchen budgets fail for a boring reason: money gets spent in the wrong order. Cabinets are chosen before the plumbing is understood, the range is ordered before anyone measures the doorway, and the contingency is treated as optional. A calm budget starts with the fixed costs and works outward.
Start with a split you can defend
For a mid-range remodel, a useful starting point looks like this. Adjust the percentages to your market, but keep the shape.
- 30% cabinetry and millwork. Doors, drawers, panels, and the labour to fit them.
- 20% labour and installation. Trades, site protection, waste removal, and project management.
- 15% appliances. Cooking, cooling, extraction, and the connections they need.
- 10% worktops and splashbacks. Templating, cutting, and edge details add up quickly.
- 10% lighting, plumbing, and electrical. The invisible work that makes the room usable.
- 10% contingency. Not a luxury. It is the price of opening a wall in an old house.
- 5% design and permits. Drawings, engineering, and the paperwork nobody enjoys.
Get the fixed costs right first
Before you fall in love with a cabinet finish, confirm three things: where the water enters and leaves, how the room vents, and whether the electrical panel can carry the appliances you want. Moving a sink six feet can cost more than upgrading every door handle in the house. If the existing layout works, protecting it is often the single biggest saving available.
Ask for separate quotes for demolition, rough-in work, and finishes. A single lump sum feels tidy, but it hides the items most likely to change.
Save here, spend there
Good places to save: cabinet internals, open shelving instead of upper cabinets, a freestanding range instead of a built-in, and consistent mid-range tiles. Good places to spend: drawer hardware, task lighting, a quiet extractor, and a worktop you can actually maintain.
- Spend on anything you touch every day: taps, handles, drawer runners.
- Save on anything behind a closed door: shelf material, back panels, internal finishes.
- Never save on waterproofing near the sink or the seal around the worktop.
A timeline that survives real life
Allow two weeks for measured drawings, four to six weeks for cabinetry and appliance lead times, and six to ten weeks for the build. Add a week for every trade that has to return twice. The most common cause of a late kitchen is not slow work — it is a decision made after the order was placed.